Lake Victoria Gold: Tembo Exploration Update (Q3 2025)

Lake Victoria Gold (LVGLF) announced its Q3 2025 exploration update detailing Bulyanhulu’s progress on six licenses acquired under the 2021 APA. Highlights include the completion of 94 line-km of GAIP surveying and the commencement of aircore drilling at the Enze target (19 holes, 419m). Diamond and RC drilling are planned for Q4 2025. Project expenditures total US$6.7M of a proposed US$9M. LVG could receive up to US$45M in contingent payments and engaged Atrium Research for services at $3,500/month for 9 months, pending TSXV approval.

“`html

Lake Victoria Gold (OTCQB: LVGLF) has released its Q3 2025 update, detailing exploration progress by Bulyanhulu (Barrick/Government of Tanzania) on six licenses acquired under the 2021 Asset Purchase Agreement (APA). The report outlines significant geophysical work and initial drilling results, hinting at the potential for new discoveries within the prolific Lake Victoria Goldfield.

Key highlights include the completion of 94 line-km of Gradient Array Induced Polarization (GAIP) surveying, a method used to map subsurface geological structures and mineralization. Aircore drilling has commenced at the Enze target, with two fences (19 holes, 419m) completed, representing an initial phase of a more expansive program planned for 945 holes and 30,750m. Diamond and RC drilling are slated for completion in Q4 2025, focusing on refining the understanding of stratigraphic layers and identifying potential repetitions of key mineralized horizons. As of September 30, 2025, project expenditures totaled US$6,659,397 against a proposed US$9,000,000 under the APA. Lake Victoria Gold stands to receive up to US$45 million in contingent payments should future discovery and resource thresholds be met. Additionally, LVG has engaged Atrium Research for research services at $3,500/month for 9 months starting November 24, 2025, pending TSXV approval.

Lake Victoria Gold (OTCQB: LVGLF) ha fornito un aggiornamento sul Q3-2025 sulle esplorazioni condotte da Bulyanhulu (Barrick/Government of Tanzania) su sei licenze vendute ai sensi dell’Asset Purchase Agreement del 2021.

Punti chiave: 94 line-km di GAIP completati; l’esplorazione con aircore è iniziata a Enze con 2 fasce di perforazione (19 buchi, 419 m) di un programma previsto di 945 buchi, 30.750 m; perforazioni diamantine e RC pianificate e mirate per completamento nel Q4 2025. Le spese del progetto fino al 30 settembre 2025 ammontano a US$6.659.397 su un programma proposto di US$9.000.000 ai sensi dell’APA. LVG potrebbe ricevere fino a US$45 milioni in pagamenti contingenti se vengano raggiunti futuri soglie di scoperta/risorsa. LVG ha incaricato Atrium Research per servizi di ricerca a $3.500/mese per 9 mesi a decorrere dal 24 nov 2025 (soggetto all’approvazione TSXV).

Lake Victoria Gold (OTCQB: LVGLF) proporcionó una actualización del tercer trimestre de 2025 sobre la exploración realizada por Bulyanhulu (Barrick/Government of Tanzania) en seis licencias vendidas bajo el Acuerdo de Compra de Activos de 2021.

Puntos clave: 94 line-km de GAIP completados; perforaciones por aire comenzaron en Enze con 2 franjas (19 agujeros, 419 m) de un programa previsto de 945 agujeros, 30.750 m; perforaciones de diamante y RC planificadas y previstas para completarse en Q4 2025. El gasto del proyecto hasta el 30 de septiembre de 2025 asciende a US$6,659,397 de un programa propuesto de US$9,000,000 bajo el APA. LVG podría recibir hasta US$45 millones en pagos contingentes si se alcanzan futuros umbrales de descubrimiento/recurso. LVG contrató Atrium Research para servicios de investigación a $3,500/mes durante 9 meses a partir del 24 de nov de 2025 (sujeto a aprobación de TSXV).

Lake Victoria Gold (OTCQB: LVGLF)가 2021년 자산 매매 계약(AAPA) 하에 판매된 6개 면허에서 Bulyanhulu(Barrick/탄자니아 정부)가 수행한 탐사를 2025년 3분기 업데이트로 제공했습니다.

주요 내용: GAIP 94 선-킬로미터 완료; Enze에서 2 펜스(19구멍, 419m)의 에어코어 시추를 시작했고, 계획된 945구멍, 30,750m의 프로그램; 다이아몬드 및 RC 시추가 2025년 4분기에 완료되도록 계획 및 목표로 설정. APA에 따른 제안된 US$9,000,000 중 프로젝트 지출은 2025년 9월 30일까지 US$6,659,397에 이릅니다. LVG는 미래 발견/자원 임계치를 달성하면 최대 US$45백만의 조건부 지급을 받을 수 있습니다. LVG는 2025년 11월 24일부터 9개월간 월 $3,500의 연구 서비스로 Atrium Research를 고용했습니다(TSXV 승인을 조건으로).

Lake Victoria Gold (OTCQB: LVGLF) a fourni une mise à jour du T3-2025 sur l’exploration menée par Bulyanhulu (Barrick/Gouvernement de Tanzanie) sur six licences vendues dans le cadre de l’Asset Purchase Agreement de 2021.

Points clés : 94 km linéaires de GAIP achevés; des forages aircore ont démarré à Enze avec 2 fences (19 puits, 419 m) sur un programme prévu de 945 puits, 30 750 m; des forages diamant et RC prévus et visés pour être terminés au T4 2025. Les dépenses du projet jusqu’au 30 septembre 2025 s’élèvent à US$6 659 397 sur un programme proposé de US$9 000 000 selon l’APA. LVG peut recevoir jusqu’à US$45 millions de paiements contingents si des seuils de découverte/ressource futurs sont atteints. LVG a mandaté Atrium Research pour des services de recherche à $3 500/mois pendant 9 mois à partir du 24 novembre 2025 (sous réserve de l’approbation de la TSXV).

Lake Victoria Gold (OTCQB: LVGLF) hat ein Q3-2025-Update zur Exploration veröffentlicht, die von Bulyanhulu (Barrick/Government of Tanzania) auf sechs Lizenzen durchgeführt wurde, die gemäß der Asset Purchase Agreement von 2021 verkauft wurden.

Wichtige Punkte: 94 Laufkilometer GAIP abgeschlossen; Aircore-Bohrungen begannen in Enze mit 2 Zäunen (19 Bohrlöcher, 419 m) eines geplanten 945 Bohrlöcher, 30.750 m-Programms; Diamant- und RC-Bohrungen sind geplant und sollen im Q4 2025 abgeschlossen werden. Projektaufwendungen bis zum 30.09.2025 belaufen sich auf US$6.659.397 eines vorgeschlagenen Programms von US$9.000.000 gemäß dem APA. LVG kann bis zu US$45 Millionen an bedingten Zahlungen erhalten, wenn zukünftige Entdeckungs-/Ressourcen-Schwellenwerte erreicht werden. LVG hat Atrium Research für Forschungsdienstleistungen zu $3.500/Monat für 9 Monate ab dem 24.11.2025 beauftragt (vorbehaltlich der Genehmigung der TSXV).

Lake Victoria Gold (OTCQB: LVGLF) قدمت تحديثاً للربع الثالث من 2025 حول الاستكشاف الذي أجرته Bulyanhulu (Barrick/حكومة تنزانيا) على ست رخص تم بيعها بموجب اتفاق شراء الأصول لعام 2021.

النقاط الأساسية: 94 كيلومتر خطي من GAIP مكتملة؛ بدأت حفر الهواء في Enze مع 2 فواصل (19 حفرة، 419 م) من برنامج مخطط 945 حفرة، 30,750 م; تخطيط وحفر ماسي و RC مخصصة لإكمالها في الربع الرابع من 2025. الإنفاق على المشروع حتى 30 سبتمبر 2025 يبلغ US$6,659,397 من برنامج مقترح بقيمة US$9,000,000 وفقاً لـ APA. يمكن لـ LVG أن تتلقى حتى US$45 مليون من المدفوعات المشروطة إذا تم الوصول إلى عتبات الاكتشاف/الموارد في المستقبل. قامت LVG بتعيين Atrium Research لتقديم خدمات بحثية بمعدل $3,500/شهر لمدة 9 أشهر ابتداءً من 24 نوفمبر 2025 (رهناً بموافقة TSXV).

Positive

  • GAIP 94 line-km completed in Q3 2025
  • Aircore program planned for 30,750m (945 holes)
  • Project spending US$6,659,397 to Sept 30, 2025
  • Up to US$45 million contingent payments under APA
  • Diamond and RC drilling scheduled to complete in Q4 2025

Negative

  • Only 419m completed of planned 30,750m AC program (early-stage)
  • Contingent payments of US$45M are conditional on future discoveries

Vancouver, British Columbia – Lake Victoria Gold Ltd. (TSXV: LVG) (OTCQB: LVGLF) (FSE: E1K) (“LVG” or the “Company”) recently shared an update on its Q3 2025 exploration program related to licenses sold to Bulyanhulu Gold Mine Limited (“Bulyanhulu”), a joint venture between Barrick Mining Corporation (“Barrick”) and the Government of Tanzania, under a 2021 Asset Purchase Agreement (APA).

During the quarter, Bulyanhulu’s exploration focused on developing refined geological and structural models to determine the potential for discovering additional Bulyanhulu-type mineralization within the Tembo Inlier claims.

Q3 2025 Exploration Highlights:

Geophysical Survey: Bulyanhulu completed 94 line-km of GAIP (gradient array induced polarization) surveying. The intent is to integrate the results into updated structural and stratigraphic interpretations.

Aircore Drilling: The geochemical aircore drilling program at the Enze target began late in the Q3 reporting period. To date, 2 fences totaling 19 holes and 419m have been completed out of a larger planned project involving 945 holes covering 30,750m across 18 fences. Initial observations from logging suggest a 15m regolith profile over basalt and felsic tuff sequences, including notable quartz-veined and moderately foliated argillite intercalations hosting smokey-grey quartz veins and sulfide boxworks.

Diamond and RC Drilling: Preliminary planning for diamond drill and RC drilling along the Itetemia trend has advanced, with five diamond fences and four RC drilling fences aiming at refining the stratigraphic context. These drilling efforts will target potential repetitions of the prospective Reef 1 and Reef 2 horizons, focusing on paleosurfaces and stratigraphic fold repetitions. The completion of this drill program is scheduled for Q4 2025.

Financial Snapshot: As of September 30, 2025, the expenditures on the project to date total US$6,659,397 out of a proposed US$9,000,000 under the APA.

Strategic Context: Contingent Payments and Upside Potential

Under the Asset Purchase Agreement (APA) executed in 2022, Lake Victoria Gold (LVG) is eligible to receive contingent payments from Barrick up to US$45 million. These payments are contingent upon future discoveries or reaching specific resource thresholds identified within these licenses, thus emphasizing the importance of ongoing explorative efforts. For investors, this arrangement presents a unique opportunity, allowing exposure to the upside of exploration success while mitigating some of the inherent geological risks. Should Barrick’s continued exploration yield significant discoveries, LVG stands to benefit substantially, providing possible future revenue streams without incurring additional capital outlay.

Management Perspective

“The Q3 data from Barrick reflects a carefully considered and technically rigorous strategy to demystify the Tembo geology,” noted David Scott, Director and Managing Director for Tanzania at Lake Victoria Gold. “The integration of the GAIP survey, extensive aircore drilling, and scheduled diamond and RC drilling all align toward a common goal – pinpointing Bulyanhulu-style mineralization within the Inlier. With the addition of deeper drilling and structural refinement, our confidence grows regarding the potential for a significant discovery.”

Marc Cernovitch, President & CEO of Lake Victoria Gold, added, “The continued progress by Barrick at Tembo reinforces the long-term potential of this highly strategic asset. Their work is helping to refine the geological picture across the Inlier and advance our collective understanding of the structures that host major gold systems in the region…Tembo provides Lake Victoria Gold with meaningful exploration upside and optionality within one of Africa’s most prolific gold belts.”

Looking Ahead

Bulyanhulu has announced that aircore drilling will continue throughout Q4 2025. The completion of diamond and RC drilling programs is expected in the same quarter. Interpretations derived from the GAIP surveys will be pivotal in guiding further refinement in drill targeting along key structures within the Tembo Inlier. The results of these activities will be closely monitored by investors, offering potential catalysts for the stock.

LVG also announced its engagement with Atrium Research Corporation to provide research reports on the company based on publicly available information, industry data, and interviews with management. Atrium is expected to release multiple reports and recorded interviews and in turn will receive $3,500 per month for 9 months with the service commencing on November 24th, 2025. This engagement is subject to TSXV approval.

FAQ

What exploration work did Barrick complete on LVG’s Tembo licences in Q3 2025 (LVGLF)?

Barrick’s Bulyanhulu completed 94 line-km of GAIP and initiated aircore drilling at Enze, completing 19 holes (419m) to date.

How large is the planned aircore program on the Tembo licences (LVGLF)?

The planned aircore program is 945 holes for 30,750m across 18 fences.

What are the project-to-date expenditures reported by Lake Victoria Gold (LVGLF) as of Sept 30, 2025?

Cumulative project spending is reported at US$6,659,397 of a proposed US$9,000,000 under the APA.

When will diamond and RC drilling be completed on the Tembo targets (LVGLF)?

Diamond and RC drilling programs are planned and expected to be completed in Q4 2025.

How much could Lake Victoria Gold (LVGLF) receive from Barrick under the APA?

LVG may receive up to US$45 million in contingent payments, subject to future discoveries or defined resource thresholds.

What engagement did LVG announce with Atrium Research on Nov 24, 2025 (LVGLF)?

LVG engaged Atrium to publish research and recorded interviews for $3,500 per month for 9 months, starting Nov 24, 2025, subject to TSXV approval.

“`