  • E3 Lithium Achieves Battery-Grade Lithium Carbonate Production in Phase 1 Demonstration

    E3 Lithium announced the successful production of battery-grade lithium carbonate during Phase 1 commissioning of its Demonstration Facility. This confirms the functionality of its direct lithium extraction (DLE) technology, achieving an average purity of 99.70% when converted to lithium carbonate. The company intends to continue operations through Q4 2025 for customer pre-qualification and potential offtake agreements. Phase 2 will involve production and injection well drilling to inform the Feasibility Study and Final Investment Decision for the Clearwater Project. E3 Lithium holds significant lithium resources in Alberta and Saskatchewan.

    2025年9月22日
  • E3 Lithium Receives Approvals for Clearwater Project Phase 2 Demo Plant

    E3 Lithium secured permits from the Alberta Energy Regulator for Phase 2 of its Clearwater Project Demonstration Facility. This allows E3 Lithium to drill production and injection wells to analyze flow rates and reservoir properties, crucial for designing its commercial well scheme. These permits are essential for operating a commercial lithium facility in Alberta, positioning E3 Lithium favorably in the market. Phase 2 follows the commencement of Phase 1 on September 2, 2025, and supports E3’s goal of validating its direct lithium extraction technology.

    2025年9月11日
  • E3 Lithium Announces Q2 2025 Financials, MD&A Filing, and Lead Director Appointment

    E3 Lithium (TSXV: ETL) released its Q2 2025 financials, highlighting progress on its Clearwater Demonstration Facility, slated for Q3 commissioning. Assembly of the Direct Lithium Extraction (DLE) system is complete and undergoing inspection. Joint development with Pure Lithium yielded promising lithium metal battery results, achieving >99.9% purity. Alexandra Cattelan was appointed Lead Director. E3 Lithium holds significant lithium resources in Alberta and Saskatchewan, with a pre-tax NPV8% of USD 5.2 Billion for the Clearwater Project.

    2025年8月27日
  • E3 Lithium Announces Clearwater Project Demonstration Plant Update

    E3 Lithium Ltd. is nearing completion of Phase 1 of its Demonstration Facility in Alberta, Canada, focused on Direct Lithium Extraction (DLE). All major equipment is assembled, and infrastructure integration is underway. Commissioning, starting with brine introduction to optimize the DLE system, is targeted for late August. The facility aims to produce high-quality lithium chloride for battery-grade lithium carbonate production. E3 Lithium holds a substantial lithium resource base and a promising Pre-Feasibility Study on its Clearwater Project.

    2025年8月12日
  • E3 Lithium Files NI 43-101 Technical Report for Updated Garrington District Resource Estimate

    E3 Lithium (TSXV: ETL) has filed its NI 43-101 technical report for the Garrington District lithium project, confirming previous resource estimates of 5.0 Mt LCE Measured and Indicated, and 0.3 Mt LCE Inferred. The report, reviewed by qualified experts, is accessible on the company’s website and SEDAR+. E3 Lithium also granted stock options to VP Rob Knowles, exercisable at $0.81. E3 Lithium holds significant lithium resources in Alberta and Saskatchewan, as detailed in their technical reports.

    2025年7月22日
  • E3 Lithium Starts Delivery of Key Equipment for Clearwater Demo Plant

    E3 Lithium Ltd. delivered key Direct Lithium Extraction (DLE) equipment, including a 30-column system, to its Clearwater Project demonstration site. This milestone advances the vital Canadian lithium project toward validation of its process. Initial operations will test equipment and aim to produce battery-grade lithium carbonate. CEO Chris Doornbos states this moves pilot results toward commercial scale, highlighting Canada’s strategic lithium supply potential. The project leverages Alberta’s significant 21.2 million tonne lithium resource base.

    2025年7月10日